Timeline
2020
May 2020
Town of Milford receives draft EPA NPDES Discharge Permit and provides comments.August 2020
MWUD solicits for engineering qualifications, conducts interviews, and selects Hoyle, Tanner & Associates, Inc. to help meet the new permit requirements.November 1, 2020
New EPA NPDES Permit becomes effective and includes timeline (54 months) to comply with advanced treatment requirements.
2021
March 2021
Engineering study begins to assess treatment alternatives to remove phosphorous and metals from the wastewater.July-August 2021
Conducted pilot study of three treatment technologies at the WWTF to meet advanced treatment requirements.September-October 2021
MWUD staff tour facilities in New England using the advanced treatment processes piloted at the Milford WWTF.December 2021
90% Basis of Design report for advanced treatment process submitted to Milford Water Utilities and NHDES for review and comment.
2022
February-March 2022
MWUD applies for ARPA Grant funds and receives $520,000 to support wastewater studies and preliminary design work.April 2022
Advanced process selection decision made, and design of advanced treatment process begins. Additional needs (age-related) identified by MWUD staff; study initiated to assess other major process elements at the Milford WWTF.May-June 2022
MWUD applied for NHDES low interest loan funds; and for an ARPA Planning Grant to study the additional needs.June 4, 2022
First open house/public tours at the Milford WWTF.August 2022
Milford approved for borrowing from the State of New Hampshire low interest loan program; Milford approved for $100,000 planning grant to study the additional needs at the WWTF.October 1, 2022
Second open house/public tours at the Milford WWTF.October 8 & 9, 2022
Hosted a booth at Pumpkinfest to inform residents about the WWTF Upgrade project and answer any questions.October 2022
60% Basis of Design Report on additional needs submitted to MWUD and NHDES.
2023
January 16, 2023 | 6:30 pm | Town Hall Auditorium
Informational session to learn more about the project. Session took place at the Town Hall auditorium at 6:30 pm.February 4, 2023 | 9:00 am
Deliberative Session to include presentation about the WWTF Upgrade Project.February 23, 2023
Interview with Granite Town Media & Dale White, Chairman of the Water & Wastewater Commissioners, to discuss this project’s warrant article.March 14, 2023 | 6:00 am – 8:00 pm | Milford High School
Town meeting vote at Milford High School 100 West Street, Milford, NH.May 2023
95% Basis of Design Report on additional needs was submitted to MWUD and NHDES.June 2023
30% design plans delivered to the Town and the New Hampshire Department of Environmental Services (NHDES) for review and comment.September 25, 2023 | 11:00 am
60% Design update presentation to the Commissioners.September 26, 2023
Value Engineering Workshop to review WWTF design to determine any changes that could be made for cost savings.December 15, 2023
95% design documents delivered to the Town and NHDES for review and final comment.
Pre-procurement of tertiary and UV equipment.
2024
January 2024
NHDES review and comment period complete. The design documents addressed NHDES comments and were submitted for approval.February 13, 2024
NHDES authorization to bid was received.February 15, 2024
Project was publicly bid.March 27, 2024 | 2:00 pm
Bid opening.April-May 2024
Construction contract is awarded & construction begins.
2025
January-December
Advanced Treatment process under construction.
2026
January-December 2026
Remaining upgrades under construction.